Payment Date (Account = Pre Payment)
When Pre Payment is selected as account, a date has to be set with the help of a Date Choice Box. On this date the expense of the whole Project Lifetime is payed. With an expense of EUR 18'000 per year and a Project Lifetime of 20 years, the capital drain on the defined date, in this case 01 / 2016, is EUR 18'000 x 20 years = EUR 360'000. When the defined date is before Transaction, the capital drain will occur at Transaction.
∑ | 01.2016 | 02.2016 | 03.2016 | 04.2016 | 05.2016 | 06.2016 | 07.2016 | 08.2016 | 09.2016 | 10.2016 | 11.2016 | 12.2016 | ... | 12.2036 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Profit & Loss statement | 360'000 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | ... | 1'500 |
Cashflow statement | 360'000 | 360'000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ... | 0 |
Payment Date (Account = Provision)
When Provision is selected as account, a date has to be set with the help of a Date Choice Box. On this date the expense of the whole Project Lifetime is payed. With a expense of EUR 18'000 per year and a Project Lifetime of 20 years, the capital drain on the defined date, in this case 12 / 2036, is EUR 18'000 x 20 years = EUR 360'000.
∑ | 01.2016 | 02.2016 | 03.2016 | 04.2016 | 05.2016 | 06.2016 | 07.2016 | 08.2016 | 09.2016 | 10.2016 | 11.2016 | 12.2016 | ... | 12.2036 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Profit & Loss statement | 360'000 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | 1'500 | ... | 1'500 |
Cashflow statement | 360'000 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ... | 360'000 |