(Project, Equity and Payout) | |
---|
NPV | |
---|
DSCR | DSCR = internal financed components of the operative Cashflow(t) / Debt Service referred to the Look Back Period |
---|
Full-load Hours | Full-load Hours = Production Amount per year / Power |
---|
Capacity Factor | Capacity Factor = Full-load Hours / ha with ha = hours per year (8760 h) |
---|
Sum Production Amount | Sum Production Amount = Production Amount x Project Lifetime |
---|
LCOE | Mathinline |
---|
body | \frac{\sum^T_{t=0} \frac{\mathrm{Cashflow to Equity}_t - \mathrm{ErlöseSales}_t)}{ (1 + \mathrm{ZielrenditeHurdle Rate}_t)^t}}{ \sum^T_{t=0} \frac{\mathrm{ProduktionProduction}_t}{(1 + \mathrm{Zielrendite}_tHurdle Rate})^t}} |
---|
|
t=0: Bewertungszeitpunkt: Valuation Date t=T: Project end |
---|